Page 9 - Vol34No7 MarchApril2017
P. 9
marina was selected due to its proximity View of the Emergency WTP from the Fall Creek Falls State Park Inn
to the arterial waterline through the park,
its suitable access road, and its distance level. Over the next nine days, the Park the day was spent strategizing how to
from the Inn and cabins due to concerns staff continually stepped up with their make things go as quickly as possible
with security and noise. The balance of resourcefulness and willingness to help when the supplies showed up. This
the first week was spent obtaining both make this plant a reality. Within 24 strategy paid off, as Garney completed all
engineering information and rental hours of being onsite, the Park staff had of the piping work in under three days.
agreements from the various equipment constructed a retaining wall, coordinated By the end of the day on Sunday, Nov.
suppliers. gravel and sand deliveries, and leveled 13, 2016, all systems had been installed
out the area needed for the mobile and disinfected and bacteria sampling
The second week was dedicated to equipment. had been collected for TDEC’s approval.
engineering the hydraulics, chemical feed, Monday morning, all of the field service
and site work associated for the treatment That grading work was completed representatives for the various equipment
system. A great deal of this was done literally minutes before the first piece of showed up to test out the systems and
in Google Earth with a comprehensive equipment, the plant clearwell, arrived on train the operators. TDEC representatives
computer hydraulic model because of the back of a TDOT lo-boy. That clearwell also were onsite to provide guidance and
the lack of record drawings of both the was a 12,000 gallon HDPE coagulant talk with the operators. The permitted
site and the water distribution systems. A storage tank supplied by the City of operation of the emergency water
number of assumptions had to be made Alcoa. The City took it upon themselves treatment plant was established using
given the lack of information and the fact to utilize their TDOT connections to have the existing operation permit held by
that months of design work was being the tank delivered to the site within a few TDOC and the Taft plant. Operators for
compressed into a week. Most of the raw days. the plant were assembled from numerous
water quality wasn’t even available from other facilities across Middle and East
the lab during this period, and only one Shortly after the arrival of the clearwell, Tennessee via an emergency contract
sample could be analyzed in the time the biggest hurdle of the process established by TDOC with Hailey
allotted. was faced. Because of the number of Management Services.
emergencies across the southeast related
Numerous conference calls were to Hurricane Matthew, the original The final day of construction involved
held with TDEC to determine the pipefitter was not going to be able getting the online instruments and lab
appropriate treatment. It was determined to make it to the site that week. SSR ready for duty. The boat ramp’s Men’s
that pretreatment prior to membrane quickly prepared a rough inventory of Bathroom was repurposed to house
filtration would not be included. The what would be required to connect the an online turbidimeter and chlorine
raw water test results indicated low equipment, and a rudimentary request analyzer. The Bait Shop was adapted
turbidity, low manganese, low alkalinity, for proposals was sent out to local to be a wet lab and operator office.
low hardness, and low conductivity. It contractors at 4:00 PM. Two proposals Hailey Management provided most of
was unlikely that traditional coagulation were received that same evening, and by the analyzers and equipment in the lab.
would even work for this water and 9:00 AM the next morning, the Park’s Columbia Power and Water Systems,
this was later proven at Murfreesboro’s procurement department had Garney Hach Instruments and MR Systems also
Stones River Water Treatment Plant lab. Construction under contract. pitched in equipment that the operators
Another concern with coagulation was would need.
that the residual chemicals in the sludge Early the next morning, the Pall mobile
could cause issues for the small lagoon treatment unit arrived behind a tractor I don’t believe I have ever seen a better
wastewater treatment plant operated by trailer rig. Unfortunately, pipe wouldn’t
the Park. It was also decided to include show up until the following morning so Continued on page 10
UV disinfection to provide an additional
barrier to pathogens because so little
source water data was available. Finally,
a system to add both hardness and
alkalinity was included in the treatment
scheme to prevent corrosion from the
extremely aggressive source water. All
of this information was summarized
in an Engineering Report that was sent
to TDEC for approval. That approval
took less than one day due to the close
coordination TDEC had with the project
team.
At the beginning of the third week,
coordination of construction began
onsite. The first hurdle was grading the
site for the mobile equipment since the
membrane train had to be relatively
View online at tnpublicworks.com 9