Page 22 - Nov/Dec Vol34 No5
P. 22
2016 CONFERENCE TECHNICAL SESSION CHATTANOOGA By Shane R. Womack
Ross’s Landing
21st Century Waterfront
Repair Design & Construction
Amid Chattanooga’s successful down- schematic design rec- Top: Anchor posts tensioned to the bedrock. Middle:
town revitalization efforts, the city’s eco- ommendations and full Pile-cap rebar installation at the mooring pocket.
nomic development group moved forward design documents, and Bottom: Cyclists enjoying the new riverfront.
with enhancements along the Tennessee oversee bid and con-
River, effectively turning a moderately struction administration Lessons Learned
equipped boat dock into a world-class for improvements and While it would be great to think that
recreation area. Built in 2005, Ross’s Land- repairs.
ing Park was the centerpiece of the City everything always goes according to plan
of Chattanooga’s 21st Century Waterfront An in-depth, above- on a major project, it often doesn’t. When
effort to entice residents and visitors to and below-water inves- portions of the 60-foot terrace beams were
embrace this picturesque section of the tigation of the entire removed from the lowest level, support
Tennessee River that intersects the city’s riverfront area revealed systems installed by the contractor were
downtown. that there was significant not fully effective and the adjacent terrace
loss of material, which beams began to shift and crack. Instead of
The park hosts numerous events, was being washed away replacing terrace beams only at the lowest
including Riverbend Music Festival, the from the terraced area level of the terraced steps, the design was
Head of the Hooch Rowing Regatta and, below the pile-supported adjusted to also replace adjacent beams
most recently, the Iron Man triathlon, river walk. Identified and supporting material, protecting the
as well as many other craft, music, and problems included: the terraced steps and walkways on either
regional festivals, drawing local, national, steep slope, erosion and side, as well as the upper sections. In the
and even international spectators and settlement of the riprap, modified design, the entire lowest terrace
participants. Ross’s Landing Park is quite which was allowing fill section was integrated into the sheet-pile
literally the “front porch for the city,” material to migrate; the wall cap.
representing both a link to its past and a concrete showed mul-
window to its future. tiple cracks; fill material was able to shift Construction included the installa-
A Crack in the Plan because it was not well-consolidated and tion of an anchored steel sheet pile wall
because it contained inconsistent and between the river walk and terraced area.
The cosmetic features of the 21st Cen- under-compacted materials; and there This anchor wall eliminated migration of
tury Waterfront project include terraced were differences between current on-site the support material below the terraces
steps from which a verdant park stretches conditions and the original construction
inland, a marina, and a generous river drawings, which resulted in unknowns
walk with wide walkways and utility- during the reconstruction process.
equipped, modern moorings for daytime
and overnight boaters. But relatively soon The flow of the Tennessee River, con-
after the project was finished by the con- trolled by dams upriver, was creating un-
struction contractor in 2005, through no derwater turbulence that was slowly erod-
fault of the city, the new sidewalk panels ing away fill material supporting the river
started to crack, settle, and collapse at walk’s structures, including the walkways
intermittent locations along the shoreline. and terraced steps. Semi-annual surges
It became apparent that settling of terrace from dam releases caused water levels to
beams, sinkholes around utility boxes, and rise as much as 12 feet, evacuating even
concrete cracks and spalls were occurring, greater amounts of fill material from
resulting in significant, and potentially beneath shoreline structures. Portions
hazardous, structural deterioration of this of the structure were literally collapsing
relatively new structure. and significant repairs were necessary to
protect the highly trafficked landmark.
HDR, a global international engineer-
ing and architectural firm with an office in The recommended design called for
Chattanooga, was selected for a multi- the replacement of only the lowest level of
year, three-phase approach to address terrace beams to facilitate the installation
the issues: evaluate and investigate the of sheet piles. These piles would form a
structure and underlying causes, provide wall to retain the fill material and prevent
it from migrating into the river.
22 TPW November/December 2016