STATEWIDE                                                                                  By Brett Ward
Water and Wastewater System
Energy Savings

  Electrical savings of tens of thousands    provide electrical demand graphs, which       guidance, and most are very familiar
of dollars, sometimes up to 30 percent,      can be very helpful in managing demand        with water and wastewater plants and
have been achieved through simple            charges. Contact your local power             the various processes. A recent TN
operational changes at wastewater plants.    company for details.                          Partnership city is using a local electrician
Quick and dramatic results don’t always                                                    to slowly upgrade facility lighting to LED
happen, but you don’t know until you         Energy Service Companies                      fixtures. Sometimes utility staff persons
begin to ask questions and dig into the                                                    also have the skills to provide these types
electrical, operational and design details.    Energy Service Companies are very           of upgrades.
For Tennessee water and wastewater           active within the state. They generally take
utilities there are several options for      a citywide look at all electrical loads and   Plant Operations
assistance in evaluating water and           will bundle high return on investment and
wastewater energy usage.                     low ROI upgrades to make an economical        Energy conservation, sustainability and
•	 Tennessee Water & Wastewater Energy       project. The ESCO fees and all upgrades       stewardship have all become popular
                                             are financed from the electrical savings.     buzzwords for any enterprise that uses
  Efficiency Partnership                     MTAS would recommend that the                 electrical equipment. It is often cited that
•	 Comprehensive Services from TVA           Qualifications-Based Selection process        35 percent of a city’s energy usage occurs
                                             be used when choosing an ESCO. Most           at water- and wastewater-treatment
  through your local power company           ESCOs also sell electrical equipment, so      plants, so these facilities generally get
•	 Energy service companies                  many of their recommendations involve         a lot of attention. For water plants,
•	EnerNOC                                    upgrading that equipment. It is good          pumping is generally the largest power-
•	 Consulting engineers                      to choose a contractor who is qualified       using activity, but water must be pumped,
•	Self-audits                                to evaluate plant processes, pumps            and in wastewater plants, aeration is
                                             and motors, as well as the electrical         the largest power-consuming activity.
Tennessee Water and Wastewater               equipment. See www.naesco.org for more        Knowing and understanding these
Energy Efficiency Partnership                information.                                  processes and the details of electrical
                                                                                           billing will help diligent managers
  This group began in 2011 as a              EnerNOC                                       and operators fulfill their missions as
cooperative effort between TDEC, Region                                                    economically as possible. See MTAS
4-EPA, TVA, the University of Memphis          EnerNOC is a third-party contractor         guidance material on understanding
and the Municipal Technical Advisory         who works within the TVA system to            the commercial electrical bill at
Service. The Partnership provides no-        assist in lowering the peak electrical        http://www.mtas.tennessee.edu. View
cost technical assistance to water and       demand. Many industries and public            several documents under “Links for City
wastewater plants and has averaged a 19      utilities already contract with them. They    Officials, Sewer, Energy and Electricity
percent savings through several rounds of    pay a modest monthly fee plus additional      Resources.”
projects. The assistance includes training   monies when the facility makes a demand
for staff and an on-site audit conducted by  response. During peak demand times              Wastewater plants often have two
Dr. Larry Moore from the University of       such as hot summer afternoons or cold         types of “low-hanging fruit” just ripe for
Memphis and Brett Ward, UT-MTAS. For         winter mornings, EnerNOC will request         the energy-conservation picking. The
more information, contact Ben Bolton at      that the electrical demand be lowered.        discharge of nitrate, either in the plant
ben.bolton@tn.gov or (615) 532-8798.         A response is not mandatory, but if the       effluent or digested sludge, represents
                                             plant rarely fulfills its demand response     potential savings, but the facility must
Comprehensive Services                       they will eventually end the contract.        have the capacity and staff must have
                                             In addition to the fees paid, one of the      the understanding of how to “denitrify”
  Most local power companies                 most useful benefits of EnerNOC is the        those processes to achieve the savings.
participate with TVA in a program called     software they will install on an on-site      Many plants also operate their biological
Comprehensive Services. This program,        computer that gives an ongoing graph          treatment units at far too high a dissolved
paid for by the local power company,         of electrical demand. This real-time tool     oxygen level and also too high a “sludge
provides engineering and technical           can be very helpful in understanding and      age” than is needed for meeting permit
assistance to commercial and industrial      thereby managing your facility’s electrical   requirements, but there are often local
customers. The program can include           demand. For more information, see             reasons for these high operational levels.
HVAC and lighting recommendations,           https://www.enernoc.com.                      Contractors who focus on equipment
infrared scans, ultrasonic testing,                                                        only often miss these areas of low-
metering equipment to gather data, power     Other Options                                 hanging fruit. It should be noted that
analysis and demand-side management.                                                       operating a wastewater plant so that it
Projects often document and recommend          Many consulting engineers can also
solutions for low power factor and can       provide excellent energy audits and