Page 9 - Nov-Dec2017 Vol35 No5
P. 9

Alcoa Highway to 22nd (Phase I) and             construction has progressed eastward.        complete to Copper Cellar, electrical duct
the new signal systems were completed                                                        bank installed to 17th, northside overhead
at University Commons and Volunteer             MAY 2016                                     electrical removals complete.
Boulevard.
                                                Water installed in South 18th, water and     AUGUST 2016
DECEMBER 2015                                   gas services to properties connected to
                                                the new mains, storm drainage in Cum-        Storm line in North 18th Street installed,
Phase I work completed on time and              berland installed to 18th, electrical duct   sidewalks and planter curbs poured at
under budget. Installed the KUB primary         banks installed to North 18th, sidewalks     North 18th Street, roadway curb in Cum-
electrical duct bank across Cumberland,         poured up to radius North 20th, Water        berland poured to east side of Walgreens,
installed north side storm drainage to          services and electrical duct bank installed  roadway curb on west side of North 19th
underground structure at Starbucks, and         across 17th, Storm drainage in Cumber-       poured, colored and pervious concrete has
installed a new water line and new sewer        land installed to 17th.                      been poured to the radius at North 18th,
line in North 20th Street.                                                                   pavers installed to North 19th, signal
                                                JUNE 2016                                    system foundations at North 18th are
JANUARY 2016                                                                                 completed.
                                                Tree well and Silva Cell excavation has
Phase II streetscape work began, 22nd to        progressed east of 19th, completed           SEPTEMBER 2016
17th Street. KUB sewer bypass in place for      water service connections in 18th south,
sewer replacement, water and gas installed      completed water service connections on       North sidewalks completed to 18th, road-
through the 19th Street intersection, new       Cumberland from 18th to 17th, Installed      way curbs and sidewalks on both sides
water services installed to Panera Bread        water main and gas main from 17th            of North 20th are complete, Starbucks
and Uptown Grill, storm sewer drain-            working east to end of project, Entrance     drive thru is complete and open to traffic,
age installed at North 21st Street and the      to Copper Cellar re-opened with new          street light poles and luminaires installed
KUB primary electrical duct bank crossed        driveway, Electrical duct bank installed     to Hibachi Factory, trolley track removal
18th street, installation of a water line was   to west side of FedEx Kinkos, Silva Cells    and excavation to subgrade for center lane
completed in North 20th.                        installed to 18th.                           completed from 22nd through North 20th
                                                                                             Street.
FEBRUARY 2016                                   JULY 2016
                                                                                             OCTOBER 2016
A new gas line was tested and in service        Tied the water main in Cumberland at
up to North 19th Street. Irrigation service     Volunteer, water line in Melrose tied in     42-inch storm drain installed to Mount-
and 6-inch line to Long Branch Saloon           at Lake Avenue, domestic service tied in     castle Street, north side lighting is active
was installed, north side storm drain-          to businesses at 17th, roadway excavation    to The House of Dragon, North 20th
age installed to the corner of North 20th.      has progressed east of North 19th, base      rebuilt and paved through binder, west-
North 19th utility work completed, North        stone installed to North 19th, sidewalks
side storm drainage installed just past                                                                                            Continued on page 10
University Liquors and street lighting duct
bank completed to Starbucks.

MARCH 2016

All sewer on the Streetscapes project
installed. Traffic delineators placed up to
17th. Water line installation in process, gas
lines crossing street installed at 21st, cable
pulled through duct bank, tree wells and
silva cells installed to 20th Street, started
installation of curb. Water line installation
in 17th Street is complete, water and gas
main are installed up to mid-block between
18th and 17th, cable pulled through the
primary duct bank in 18th, storm drain-
age installation in North 20th is complete,
tree well and Silva Cell installation has
progressed to the Shell station and the
roadway curb poured to Insomnia Cookies.

APRIL 2016

Water main connection in Cumber-
land at South 19th is complete. Storm
drainage in Cumberland has progressed
to Copper Cellar, overhead electrical
removals from North 20th to North
18th completed, tree wells and Silva cells
progressed to mid-block between 20th
and 19th, entrances in 2100 block are all
poured and re-opened, Roadway curb

                                                	                                            View online at tnpublicworks.com	  9
   4   5   6   7   8   9   10   11   12   13   14