Alcoa Highway to 22nd (Phase I) and construction has progressed eastward. complete to Copper Cellar, electrical duct
the new signal systems were completed bank installed to 17th, northside overhead
at University Commons and Volunteer MAY 2016 electrical removals complete.
Boulevard.
Water installed in South 18th, water and AUGUST 2016
DECEMBER 2015 gas services to properties connected to
the new mains, storm drainage in Cum- Storm line in North 18th Street installed,
Phase I work completed on time and berland installed to 18th, electrical duct sidewalks and planter curbs poured at
under budget. Installed the KUB primary banks installed to North 18th, sidewalks North 18th Street, roadway curb in Cum-
electrical duct bank across Cumberland, poured up to radius North 20th, Water berland poured to east side of Walgreens,
installed north side storm drainage to services and electrical duct bank installed roadway curb on west side of North 19th
underground structure at Starbucks, and across 17th, Storm drainage in Cumber- poured, colored and pervious concrete has
installed a new water line and new sewer land installed to 17th. been poured to the radius at North 18th,
line in North 20th Street. pavers installed to North 19th, signal
JUNE 2016 system foundations at North 18th are
JANUARY 2016 completed.
Tree well and Silva Cell excavation has
Phase II streetscape work began, 22nd to progressed east of 19th, completed SEPTEMBER 2016
17th Street. KUB sewer bypass in place for water service connections in 18th south,
sewer replacement, water and gas installed completed water service connections on North sidewalks completed to 18th, road-
through the 19th Street intersection, new Cumberland from 18th to 17th, Installed way curbs and sidewalks on both sides
water services installed to Panera Bread water main and gas main from 17th of North 20th are complete, Starbucks
and Uptown Grill, storm sewer drain- working east to end of project, Entrance drive thru is complete and open to traffic,
age installed at North 21st Street and the to Copper Cellar re-opened with new street light poles and luminaires installed
KUB primary electrical duct bank crossed driveway, Electrical duct bank installed to Hibachi Factory, trolley track removal
18th street, installation of a water line was to west side of FedEx Kinkos, Silva Cells and excavation to subgrade for center lane
completed in North 20th. installed to 18th. completed from 22nd through North 20th
Street.
FEBRUARY 2016 JULY 2016
OCTOBER 2016
A new gas line was tested and in service Tied the water main in Cumberland at
up to North 19th Street. Irrigation service Volunteer, water line in Melrose tied in 42-inch storm drain installed to Mount-
and 6-inch line to Long Branch Saloon at Lake Avenue, domestic service tied in castle Street, north side lighting is active
was installed, north side storm drain- to businesses at 17th, roadway excavation to The House of Dragon, North 20th
age installed to the corner of North 20th. has progressed east of North 19th, base rebuilt and paved through binder, west-
North 19th utility work completed, North stone installed to North 19th, sidewalks
side storm drainage installed just past Continued on page 10
University Liquors and street lighting duct
bank completed to Starbucks.
MARCH 2016
All sewer on the Streetscapes project
installed. Traffic delineators placed up to
17th. Water line installation in process, gas
lines crossing street installed at 21st, cable
pulled through duct bank, tree wells and
silva cells installed to 20th Street, started
installation of curb. Water line installation
in 17th Street is complete, water and gas
main are installed up to mid-block between
18th and 17th, cable pulled through the
primary duct bank in 18th, storm drain-
age installation in North 20th is complete,
tree well and Silva Cell installation has
progressed to the Shell station and the
roadway curb poured to Insomnia Cookies.
APRIL 2016
Water main connection in Cumber-
land at South 19th is complete. Storm
drainage in Cumberland has progressed
to Copper Cellar, overhead electrical
removals from North 20th to North
18th completed, tree wells and Silva cells
progressed to mid-block between 20th
and 19th, entrances in 2100 block are all
poured and re-opened, Roadway curb