TULLAHOMA By Shannon Carey
Quality Fix for Safer Sidewalks
Managing public infrastructure is Before (left): Shifting soil over time has created an uneven section at the joint on this sidewalk. After
a balancing act. Walking the fine line (right): Precision Concrete Cutting creates an incline and smooth transition to remove the trip hazard.
between available funds and needed
repairs is a recipe for stress. If you’re a sidewalks. We document anything over a was that their sidewalks contained trip
municipality in charge of sidewalks, you quarter inch,” Norris said. hazards throughout them. The uneven
know those come with their own set of sidewalks were created by tree roots,
challenges as the sidewalks age. They also documented anything freezes and thaws, and expansive soils.”
that was beyond the scope of Precision
The City of Tullahoma partnered over Concrete Cutting’s work and would require One aspect that made the work in
the last two years with Precision Concrete removing and replacing concrete. All this Tullahoma unique was the nature of
Cutting for a cost-saving, quality fix for information was compiled into a detailed the concrete itself. The work spanned
their aging sidewalks, making them safer survey of the area, including a map and one or two historic districts, and Norris
and easier for pedestrians to use. longitude and latitude coordinates for said PCC’s method helps maintain the
potential problem spots, all in a GIS-ready integrity of historic neighborhoods’
Joseph Norris is the owner and president format. sidewalks without mismatched concrete
of Precision Concrete Cutting (PCC) patches.
for Alabama and Tennessee. Across the “We cast a net over everything we’re able
nation, PCC has been implementing its to repair and turn over the detailed data of “We run into all types of concrete,
sidewalk repair method since 2002. But the areas we’re not able to repair,” Norris different hardnesses, ages, etc.,” he said.
Norris said the service is more in demand said. “It allows the entity to have everything “This was very old concrete. When it is
than ever before, as local and national repaired possible at that reduced rate and old concrete, it may be a little more brittle
focus turns to The Americans with only remove and replace what they have or feeble, or sometimes it has cured its
Disabilities Act (ADA) compliance for to.” whole life and is incredibly hard. We want
sidewalks. to make sure we’re taking care of what’s
In all, PCC identified about 650 sidewalk out there. In historic districts, we’re able to
“We have shifted into becoming areas in need of repair, and about 10 salvage that historic concrete. We make it
experts on ADA compliant sidewalks percent of those needed to be removed and a real point to be incredibly timely, but to
and walkways,” Norris said. “We get calls replaced, a figure Norris said is typical of make sure we treat that area as a historic
to implement a maintenance plan while other jobs. area. People have walked on that for
keeping budgets in consideration.” generations past, and we want to preserve
Work was completed in two phases that by making sure that the finish is
The company is currently working with in July 2017 and May 2018. PCC’s team aesthetically up to standard.
the cities of Nashville, Memphis, Jackson measures the vertical displacement, then
and Gallatin, along with other Tennessee cuts the elevated portion of sidewalk to “We use a hand tool. These guys are
municipalities to address their sidewalk ADA specifications and creates a smooth using their hands, not running a machine
safety hazards. transition at the joint. Because they’re not over it or scarifying it like a grinder.”
removing and pouring concrete, they can
Norris called sidewalks a city’s corridors, make a high volume of repairs quickly and Norris estimated that PCC’s method
connecting one district or neighborhood efficiently, an average of eight to 12 minutes over rip-and-repour saved Tullahoma
with another and contributing to the per repair, which in turn keeps costs low. around $500,000. He said municipalities
attractiveness and beautification of an who are interested in having Precision
area. But, they are also subject to wear and The areas of work in Tullahoma included Concrete Cutting bring their sidewalks
tear from use and natural forces. Freezing East Grundy Street from Northeast Atlantic into ADA compliance can start with a
and thawing, shifting soil, invasive tree Street to North College Street, Jackson pilot job to allow the city to assess PCC’s
roots, all can cause vertical displacement Street North to Jackson Street South, and performance.
of sidewalks along expansion joints Stone Boulevard from Wilson Avenue to
and cracks. This creates dangerous trip West Lincoln Street. “Our push right now is to build those
hazards for walkers with no disabilities relationships in Tennessee and show those
and an impassable thoroughfare for “The sidewalks the city designated for us municipalities how we can assist, how we
those in wheelchairs. And, it exposes the to repair included neighborhoods and high can be a tool in the belt,” said Norris.
entities responsible for sidewalks to costly traffic areas,” said Norris. “The problem
litigation.
In Tullahoma, the process started with
meetings, getting to know City officers
and department heads, and understanding
the “high priority or high traffic” sidewalk
areas, Norris said.
Then, the PCC team hit the streets.
“We were boots on the ground, with
measuring tools, surveying for uneven
26 TPW September/October 2018